29th September 2013 Scaffold erected around the chancel for access to the roof. 9th October 2013 A scaffold tent has been erected above the chancel roof and a platform to give access for the work. 19th October 2013 The roof of the chancel has been completely removed leaving only the arch beams in place. 16th November 2013 Open day in the church to view damage caused by Death Watch Beetles. 15th March 2014 Second open day to see repaired trusses prior to closure by roof covering. 25th - 30th June 2014 Digging  of soak-aways for drainage of roof in entrance paths to church. During the excavation human remains were uncovered, follow link for details.